  • The power surplus in the state is being sold outside the state through a trading company which facilitates additional revenue.
  • Integration of Sikkim in the Transmission Network of the Eastern Region has been achieved with the commissioning of 132 KV lines from Rangit to Melli and construction of 132/66 KV 100 MVA Substation at Melli.
  • Effective measures are being taken to reduce both the technical and the non-technical losses, especially the non-technical losses by introducing Energy Audit by proper monitoring on all feeders and at distribution transformerlevel to identify high loss areas. The augmentation and strengthening of sub-transmission and distribution system will reduce technical losses.
  • The Diesel Power House at Gangtok was upgraded to 4 MW from the previous capacity of 1.7 MW in 1998.
  • 60 MW Rangit Hydel project in West Sikkim was commissioned in 1999.
  • 2 MW Kalez Khola power project in Dentam in West Sikkim and 3 MW Rabomchu power project in North Sikkim were commissioned in 1995-96 and 1998, respectively.
  • 132 KV transmission line from Rangit to Melli was completed in 2006. Construction of similar transmission lines from Sagbari, Gyalshing to Pelling and Ravangla is currently under execution.Another 132/66 KV sub station LLHP near Gangtok has been commissioned.
  • By 2010, all the 22 power projects of the state will be completed. From these projects the Government of Sikkim will get12 % of free power. This is likely to meet the power shortfall in State and will generate lot of revenues.
  • The state will be earning Rs. 600 crore revenue from these projects.
  • 100 % of the jobs generated in these power projects are being given to the local people depending upon their qualifications. All works which can be carried out by local contractors are being given to them.
Navigation  
 
 
  NLCPR
 
  R-APDRP
 
 
 
Site Map of Hydel Project
 
 
Introduction :
 
The 71MW Sada-Mangder Hydroelectric Power Project is 70kms from by road from Singtam in West District of Sikkim and 66kms from Bagdogra airport,West Bengal
 
     
  Location : West District
  Stream : Rangit and Relli
  Vicinity : Ravangla
 
 
Project Highlights :
 
The Sada-Mangder Hydroelecrtic Power Project is located in the West District of Sikkim on the river Rangit and Relli.The Rangit river is the second largest river in the Sikkim and a tributary of the Teesta river which is the main river of the state of Sikkim.The Sada-Mangder Hydro Elecrtic power project envisages two peaking power plants with a common underground powerhouse,common tailrace tunnel, common outdoor switchyard comprising two dams each with a storage reservoir and an intake. The upstream water conveyance system of the Sada plant comprises of the headrace tunnel,an underground surge shaft and an inclined pressure shaft,while the Mangder plant consists only of a presure shaft and a generating unit in the same powerhouse but independent in operation.
 
 
  Rainfall : 250-300 cm p.a
     
  Dam(Sada)  
  Type : Concrete,Gravity
  Dam height : 45.9 m
  Dam Volume : 37,000 m3
     
  Dam(Mangder)  
  Type : Arch
  Dam height : 47.3 m
  Dam Volume : 25,500 m3
   
  Headrace Tunnel(Sada)
  Length : 3558 m
  Internal Diameter : 2.7 m
     
  Surge Shaft  
  Internal Diameter : 12 m
  Height : 53.9 m
     
  Power House  
  Type : Out door
  Turbine type : Francis,vertical
  Generators : 1 Generator of -- MW capacity
       
 
  • To get your Bill alongwith the Print Out...Click here
  • To receive your Bill at your e-mail...Click here
  • To receive your Bill at your Mobile...Click here
  • Under Departmental Process
  • Under Departmental Process
  • To calculate your tariff...Click here
    © Copyright Notice | Privacy Statement | Feedback & Suggestion | Disclaimer | Contact Us
    All Right reserved by the Energy & Power Department, Government of Sikkim
    Site Designed & Powered by SDS SOLUTION