| Introduction : |
| |
| The 99MW Chuzachen Hydroelectric Power Project is about 60 Kms from Gangtok (Sikkim) and 100 Kms from Bagdogra Airport (West Bengal) |
| |
| |
|
|
| |
Location : |
East District of Sikkim |
| |
Stream : |
Rangpo and Rongli |
| |
Vicinity : |
Chuzachen Village |
| |
| |
| Project Highlights : |
| |
Chuzachen a (Run-of-the-River) Hydroelectric Power Project with two interconnected reservoirs with an installed capacity of 99MW.
The Rangpo river is a major tributary of the Teesta river which is the main river of the state of Sikkim.The Chuzachen has two intakes each with a storage reservoir and headrace tunnel each joining together to a common headrace tunnel,an underground surge shaft,a surface penstock and open air powerhouse with two units and an outdoor switchyard. |
| |
| |
| |
Rainfall : |
250-300 cm p.a |
 |
| |
Dam(Rangpo) |
|
| |
Type : |
Concrete,Gravity |
| |
Dam height : |
48 m |
| |
Dam Volume : |
83,000 m3 |
| |
Dam(Rongli) |
|
| |
Type : |
Concrete,Gravity |
| |
Dam height : |
41 m |
| |
Dam Volume : |
45,200 m3 |
| |
Headrace Tunnel(Rangpo) |
| |
Length : |
2578 m |
| |
Internal Diameter : |
3.3m |
| |
Headrace Tunnel(Rongli) |
| |
Length : |
2258 m |
| |
Internal Diameter : |
4m |
| |
Common Headrace Tunnel(Chuzachen) |
| |
Length : |
3225 m |
| |
Internal Diameter : |
4.6 m |
| |
Surge Shaft |
|
| |
Internal Diameter : |
12 m |
| |
Height : |
103.9 m |
| |
Surface Penstock |
|
| |
Length :
|
801.2m |
| |
Diameter : |
3.3m |
|
Power House |
|
| |
Type : |
Out door |
| |
Turbine type : |
Francis,vertical |
| |
Generators : |
2 Nos. each 49.5 mw |
| |
|
|
|
|
| |