Details of NLCPR Projects under Energy and Power Department showing the financial position
in respect to fund received  and expenditure incurred .( Provisional)
  Statement - III  
  2007-08
SL No. Name of Project under NLCPR Cost of the project Sanctioned NLCPR support (90+10)% NLCPR         share Balance fund to be received  Actual 2002-03 Actual 2003-04 Actual 2004-05 Actual 2005-06 Actual 2006-07 Cumulative exp. Upto 31.3..2007 Expenditure wef1.4.07-31.3.08 (2007-08 Unutilized fund in hand as on  31.03..07 Budget provision 2007-08 Cum. Exp. of the projects till March 07  
1 2 3 4 5 6(4-5) 7 8 9 10 11 12( 7+8+9+10+11+13) 13 14(5-12) 15 16 17
1 132 KVA lines from Rangit Melli (ongoing scheme) 2817.42 2817.42 2817.42 0.00 1303.31 1199.85 313.42 0.00 0.00 2816.58   0.84 0.00 2816.58  
1161.58 0.00 0.00 0.00 0.00 0.00 810.87 0.00 0.00 810.87   0.00 100.00 810.87  
3979.00 2817.42 2817.42 0.00 1303.31 1199.85 1124.29 0.00 0.00 3627.45 0.00 0.84 100.00 3627.45  
2 Remodelling of Transmission and Dist .network in Gangtok town, Sikkim 2988.46 2244.40 2244.40 0.00 0.00 0.00 899.71 375.53 674.90 1950.14   294.26 294.26 1950.14 Rs.1209.96 Sanctioned vide DoNER/43/2003-NLP(SKM) dated 27.12.2005 
3 Extension of 132 KV system in south & west dists of Sikkim covering Gyalshing, Pelling & Rabongla 3063.00 2303.15 1601.59 701.56 0.00 0.00 134.81 672.24 714.73 1521.78   79.81 781.00 1521.78 Rs. 715 lakhs sanctioned DoNER/44/2003-NLP9SKM) 11.9.05
4 Cost. Of 66 KV S/s to Chungthang S/s & 2*5 MVA transformer bay at Chungthang and one feeder bay at Mayong in North Sikkim 941.00 683.99 683.99 0.00 0.00 0.00 247.50 152.42 196.58 596.50   87.49 87.49 596.50 Rs.216 lakhs sanctioned Doner 41/2002-NLP SKM 9.01.06 Rs/ 264.60 lakhs sanctioned  DoNER/41/2003-NLP(SKM) 21.6.2006
5 66KV DC transmission lines from LLHP  to Bulbuley ( Sklub-transmission & dist projects at three locations) 1741.82 1561.56 1297.00 264.56 312.59 82.23 353.30 338.18 188.71 1275.01   21.99 21.99 1275.01 Rs. 189 lakhs recd vide sanction no. DoNER/25/2002-NLP(SKM) 8.3.06
6 Centralized Load Dispatch centre in Sikkim 1057.45 974.16 974.16 0.00 0.00 30.05 268.25 399.11 109.31 806.72   167.44 167.44 806.72 Rs. 360 lakhs sanctioned DONER 23/2002-NL SKM 9.01.06
7(a) Const. of 132 KV Transmission line ( to be initially charged at 66 KV) from 132/66 KV PGCIL's SS near LLHP to Sherathang incl.66KV/11KV 2*5 MV ss at Serathang near Nathula 3127.87 2845.70
 
                      Rs. 907.8 lakhs DoNER/53/2005-NLP(SKM) dated 5.9.2006 Cabinet Sanction 19.2.07 Rs. 3383.04 lakhs
7(b) 66/11 KV, 2#5 MVA substation at Sherathang near Nathula East Sikkim 255.17 255.17                        
  Total 7(a) +7(b) 3383.04 3100.87 1008.67 1837.03 0.00 0.00 0.00 0.00 929.40 929.40   79.27 844.13 929.40
8 Synchronisation of Rothak,Rimbi States I&II and Kalez Khola  to common grid associated  civil works 962.32 962.32 336.81 625.51 0.00 0.00 0.00 0.00 278.23 278.23   58.58 395.39 278.23 Adm. Approval communicated by GOI on 07/03/2006. Rs. 303.13 lakhs released as 1st instl. DONER/55/2005-NLP(SKM) 27.03.06
  Grand Total  17860.92 14392.70 10964.04 3428.66 1615.90 1312.13 3027.86 1937.48 3091.86 10985.23   789.68 2691.70 10985.23    
  State Plan
Note: These figures are all  provisional subject to reconciliation of the Accounts with the Office of the Accountant General, Sikkim. & with the Office of the Project Heads of this dept.
Note: Sl. No. 7 Cabinet sanction accorded for Rs. 278.70 Lakhs ( 299.90-21.20 ( NLCPR support)= Rs. 278.70 Lakhs on 26 the August, 2006  281/Power/works/cir-11/05-06  19 Kms 11 KV transmission line from Changu to Sherathang .This has to be projected in the Plan documents/ Plan budget of 2007-08